FavoritePlease sign in to add this to your favorites. Topic: Hydronic Heating (Hot Water and Steam) Subtopic: Equipment Installation Desired Outcome: Improved pump efficiency and control Multifamily HomesPrintCopy to ExcelEmail TitleSpecification(s)Objective(s) 5.3102.8a Check for presence of asbestos-containing materials (ACMs) Potential ACMs will be handled in accordance with SWS 2.0110.2 Potential Asbestos-Containing Materials Ensure a safe work environment 5.3102.8b Isolate pump location Nearest valves on either side of pump location will be closed Power supply will be disconnected Eliminate water and power supply to the pump location 5.3102.8c Replace pump with electrically commutated motor (ECM) pump Existing pump will be removed and replaced with ECM pump, installed in accordance with manufacturer specificationsGauges will be installed on inlet and outlet sides of pump locationSystem will be refilled, and air will be eliminatedPower will be restored to new ECM pumpPump speed variation will be verified by exercising some valves in the system, simulating load demand changes Ensure proper operation of ECM pump 5.3102.8d Reinsulate area Where insulation was removed, valve will be reinsulated with new insulation to IECC IECC International Energy Conservation Code and ASHRAE ASHRAE American Society of Heating, Refrigerating and Air-Conditioning Engineers, www.ashrae.org 90.1, at a minimum Reduce energy lossMaintain safe surface temperature 5.3102.8e Educate building operations staff Building operations staff will be educated to operate ECM pump Ensure continued optimized performance Previous Detail Next Detail Back to 5.3102 Equipment Installation Back to Top