5.3003.21a
Validate air distribution system installation System will be checked for existence of specified system components
Confirm installed system
Become familiar with system components
Verify system readiness for testing
5.3003.21b
Testing equipment selection Measurement equipment will be selected so that design value will be within the accurate range of the measuring device
Equipment will be capable of accurately measuring +/- 10% in general case
Measurement equipment will be calibrated and field checked in accordance with manufacturer recommendations
Ensure accurate measurements of airflow rates
5.3003.21c
Test air handler unit Equipment testing will check for:
Proper operation (programmed schedule/sequence of operation) Proper rotation All measured values will be recorded and compared against design specifications
Fan flow will be adjusted to meet design specification
Verify performance of air handler system
5.3003.21d
Total air flow Total system airflow will be measured in accordance with
ANSI
ANSI
American National Standards Institute, www.ansi.org
/
ACCA
ACCA
Air Conditioning Contractors of America, www.acca.org
Standard 5 or
ANSI
ANSI
American National Standards Institute, www.ansi.org
/
ASHRAE
ASHRAE
American Society of Heating, Refrigerating and Air-Conditioning Engineers, www.ashrae.org
Standard 111 and adjusted to meet design requirements
Examples of acceptable methods include the following:
Temperature rise test Air flow plate (e.g., TrueFlow® Air Handler Flow Meter) Fan pressurization device (e.g., Duct Blaster®, DuctTester) Hot wire anemometer Ensure equipment operates as designed
Ensure equipment operates efficiently
Ensure equipment provides comfort
Ensure equipment operates safely
Ensure equipment is durable
5.3003.21e
External static pressure External static pressure will be in accordance with manufacturer specifications
Ensure equipment operates as designed
Ensure equipment operates efficiently
Ensure equipment provides comfort
Ensure equipment operates safely
Ensure equipment is durable
5.3003.21f
Pressure drop: coil Pressure drop across cooling coils will be in accordance with manufacturer specifications
Ensure equipment operates as designed
Ensure equipment operates efficiently
Ensure equipment provides comfort
Ensure equipment operates safely
Ensure equipment is durable
5.3003.21g
Pressure drop: filter Pressure drop across filter will be in accordance with manufacturer specifications
Ensure equipment operates as designed
Ensure equipment operates efficiently
Ensure equipment provides comfort
Ensure equipment operates safely
Ensure equipment is durable
5.3003.21h
Balance of room flow: new ductwork Airflow will be measured in accordance with
ANSI
ANSI
American National Standards Institute, www.ansi.org
/
ACCA
ACCA
Air Conditioning Contractors of America, www.acca.org
Standard 5 or
ANSI
ANSI
American National Standards Institute, www.ansi.org
/
ASHRAE
ASHRAE
American Society of Heating, Refrigerating and Air-Conditioning Engineers, www.ashrae.org
Standard 111 and adjusted to meet design requirements
Examples of acceptable methods include the following:
Air flow will be measured at each register and compared to load calculation to ensure proper air flow delivery Adjustments will be made to fan speed, dampers, and registers until design specifications are met Ensure equipment operates as designed
Ensure equipment operates efficiently
Ensure equipment provides comfort
Ensure equipment operates safely
Ensure equipment is durable
5.3003.21i
Supply wet bulb and dry bulb Supply wet bulb and dry bulb air temperatures will be recorded
Ensure equipment operates as designed
Ensure equipment operates efficiently
Ensure equipment provides comfort
Ensure equipment operates safely
Ensure equipment is durable
5.3003.21j
Return wet bulb and dry bulb Return wet bulb and dry bulb air temperatures will be recorded
Ensure equipment operates as designed
Ensure equipment operates efficiently
Ensure equipment provides comfort
Ensure equipment operates safely
Ensure equipment is durable
5.3003.21k
Temperature rise: gas and oil furnaces only Temperature rise between the supply and return will be in accordance with manufacturer specifications
Ensure equipment operates as designed
Ensure equipment operates efficiently
Ensure equipment provides comfort
Ensure equipment operates safely
Ensure equipment is durable
5.3003.21l
Final balance Final air flow and/or pressure will be measured, confirmed, and recorded at air handler and registers
Airflow will be measured in accordance with
ANSI
ANSI
American National Standards Institute, www.ansi.org
/
ACCA
ACCA
Air Conditioning Contractors of America, www.acca.org
Standard 5 or
ANSI
ANSI
American National Standards Institute, www.ansi.org
/
ASHRAE
ASHRAE
American Society of Heating, Refrigerating and Air-Conditioning Engineers, www.ashrae.org
Standard 111 and adjusted to meet design requirements
Provide acceptable thermal comfort, energy efficiency, and indoor air quality
5.3003.21m
Occupant/property manager education Occupant/property manager will be:
Instructed on proper operation and maintenance procedures Educated on value and need for recommissioning requirements Property manager will complete a 30-hour
OSHA
OSHA
U.S. Occupational Safety and Health Administration, www.osha.gov
safety education course Ensure continued operation of equipment at design performance levels