4.1301.2b
Netting, fabric When using netting or fabric, staples will be placed according to manufacturer specifications
Netting or fabric will meet local fire codes
Secure insulation
4.1301.2c
Installation Insulation in netted or fabric cavities will be dense packed with loose fill insulation in accordance with manufacturer specifications
Insulation will be installed to prescribed R-value
Insulation will be in continuous contact with
air barrier
Air barrier
The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary
Insulate to prescribed R-value
Ensure a continuous
thermal boundary
Thermal boundary
The separation between the interior and exterior environments of a building that slows heat flow
between conditioned and unconditioned space
4.1301.2d
Occupant education A dated receipt signed by the installer will be provided that includes:
Insulation type
Coverage area
R-value
Installed thickness and minimum settled thickness
Number of bags installed in accordance with manufacturer specifications Document job completion to contract specifications
Confirm amount of insulation installed
Ensure ability to match bags required for total area completed
Comply with 16 CFR 460.17