4.1102.1a
Sealing Holes and penetrations will be sealed
Bypasses will be blocked and sealed
Prevent air leakage
4.1102.1b
Installation Insulation will be installed in accordance with manufacturer specifications without gaps, voids, compressions, misalignments, or wind intrusions
Insulation will be installed to prescribed R-value
Insulate to prescribed R-value
4.1102.1c
Pre-drywall verification Verification of complete installation without gaps, voids, compressions, misalignments, or wind intrusions will be provided
Install insulation correctly
4.1102.1d
Onsite documentation A dated receipt signed by the installer will be provided that includes:
Insulation type
Coverage area
R-value
Installed thickness and settled thickness (settled thickness required for loose-fill only)
Number of bags installed in accordance with manufacturer specifications (for loose-fill only) Document job completion to contract specifications
Confirm amount of insulation installed
Comply with 16 CFR 460.17