4.1101.1a
Preparation Lead and asbestos safety procedures will be followed
Cavities will be free of hazards, intact, and able to support
dense pack
Dense pack
The process of installing loose-fill insulation to reduce air flow and perform to a stated R-value
pressures
Drilling hazards (e.g., wiring, venting, fuel piping) will be located
Blocking will be installed around:
All openings to inside crawl space and basement for fibrous material High temperature fire-rated materials Wiring and electrical hazards Heat sources Access to exterior wall cavities will be gained, sheathing will be drilled as needed and probed to locate each cavity, wall studs, and blockers
Interior will be masked and dust controlled during drilling when accessing from interior
Electricity supply will be confirmed and will support blowing machine power demand
Blowing machine pressure test will be performed with air on full, feed off, agitator running, and gate closed
Hose outlet pressure will be at least 80
IWC
IWC
Inches of water column
or 2.9
psi
Psi
Pounds per square inch
for cellulose insulation; for other types of
dense pack
Dense pack
The process of installing loose-fill insulation to reduce air flow and perform to a stated R-value
insulation, check manufacturer specification for blowing machine set up
Prevent damage to house
Provide a clean work space
Provide thorough access to allow 100% coverage
Ensure proper equipment and process results in consistent density
Prevent settling and retard air flow through cavities
Protect worker and occupant health
4.1101.1b
Exterior
dense pack
Dense pack
The process of installing loose-fill insulation to reduce air flow and perform to a stated R-value
Using fill tube, 100% of each cavity will be filled to a consistent density:
Cellulose material will be installed to a minimum density of 3.5 pounds per cubic foot Loose fiber glass material will be installed and will be specifically approved for air flow resistance per manufacturer's specifications The number of bags installed will be confirmed and will match the number required on the coverage chart
Insulation density will be verified by bag count, core sampling, or infrared camera with the blower door at 50 pascals to prevent visible air movement using chemical smoke at 50 pascals of pressure difference
Eliminate voids and settling
Minimize framing cavity air flows