3.1001.4a
Work assessment Installer prework assessment will be conducted to determine:
Structural integrity Roof leaks Insect infestation Accessibility Number, type, size, and location of penetrations Ensure work space is safe and ready for air sealing
Verify scope of work
3.1001.4b
Air sealing penetrations Backing or infill will be provided as needed to meet the specific characteristics of the selected material and the characteristics of the penetration or hole
The infill or backing will not bend, sag, or move once installed
All accessible damaged
vapor barrier
Vapor barrier
A material that retards the passage of water vapor and contains a perm rating of less than 1
will be repaired
Penetration through the
air barrier
Air barrier
The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary
will be repaired
Ensure closure is permanent and supports any load (e.g., wind, insulation, mechanical pressures)
Ensure sealant is effective and durable
3.1001.4c
Sealant selection Sealants will be used to fill holes no larger than recommended by manufacturer specifications
Sealants will be compatible with all adjoining surfaces
Sealants will be continuous and meet fire barrier specifications, according to authority having jurisdiction
Create a permanent seal
Ensure sealant meets or exceeds the performance characteristics of the surrounding materials
Create a continuous seal
3.1001.4d
Ceiling hole repair Ceiling repair material must meet or exceed strength of existing ceiling material
Ceiling repair must span from truss to truss or add blocking as needed for support
The backing or infill will not bend, sag, or move once installed
All accessible damaged vapor barriers will be repaired
Penetrations through the
air barrier
Air barrier
The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary
must be repaired
Ensure ceiling is structurally sound
Minimize air leakage
Ensure closure is permanent and supports expected wind and mechanical pressure loads
Ensure sealant does not fall out
3.1001.4e
Materials Materials will be used or installed in accordance with product manufacturer specifications
Select materials to ensure durable and permanent repair
3.1001.4f
High temperature application Only noncombustible materials will be used in contact with chimneys, vents, and flues
Local codes will be referenced
Prevent a fire hazard